Georgia Public Service Commission Releases Staff Review of Southern Nuclear Company’s Vogtle Forecast Schedule and Cost
Monday, August 12th, 2019
The Georgia Public Service Commission Staff on Tuesday released its review of Southern Nuclear Company’s April 2019 Vogtle Units 3 and 4 Re-baseline of Forecast Schedule and Cost.
The report is available here: https://psc.ga.gov/search/facts-document/?documentId=177914
Georgia Power must file under docket 29849 its next combined 20th and 21st Semi-Annual Vogtle Construction Monitoring (“VCM”) Report on August 31st, 2019. This VCM report will include updates on actual costs spent through June 30th, 2019 and an update on its forecasted costs and schedule to reach commercial operation of both Units.
The Georgia Public Service Commission is a five-member constitutional agency that exercises its authority and influence to ensure that consumers receive safe, reliable, and reasonably-priced telecommunications, electric and natural ga